The Green Blocks Pilot Project will be implemented in phases with some occurring simultaneously.
Phase I: Recruit residential city blocks in Seattle to participate and conduct home performance assessments
Start Date: June 1, 2009
End Date: August 28, 2009
Phase II: Apply performance assessment recommendations
Start date: September 1, 2009
End date: June 30, 2010
Phase III: Conduct a feasibility study for deploying neighborhood clean energy technology (PV, solar thermal, geothermal)
Start date: January 1, 2010
End date: June 30, 2010
Phase IV: Implement recommendations from the clean energy technology feasibility study
Start date: July 1, 2010
End date: December 31, 2011